Bridge Replacement – N203

Project and Procurement Workspace

Tender Preparation
Project Scenario

This project explores the use of verified infrastructure components to support circular design and procurement decisions.

Project Name

Bridge Replacement – N203

Client

Province of North Holland

Asset Type

Road Bridge

Location

N203, km 12.5

Procurement Procedure

Open Tender

Stage

Tender Preparation

Design Life Requirement

50 years

Tender Requirements

Technical Requirements

Minimum Span
20–30 m
Design Standard
Eurocode EN 1992
Load Class
LM1
Concrete Class
C40/50 or higher

Circularity Requirements

  • Reuse preferred where feasible
  • Demountability required
  • Lifecycle extension preferred
  • CO2 reduction considered

Evidence Requirements

  • Inspection ReportSatisfied
  • Structural Capacity AssessmentSatisfied
  • Material VerificationSatisfied
  • DPP LinkSatisfied
  • Verifier IdentifiedUnresolved
Selected Components
Component IDTypeSpanCondition ScoreVerification StatusReuse PotentialProcurement Relevance
DEMO-GIRDER-01Precast Girder24.5 m3VerifiedHighSuitable
DEMO-BEAM-02Box Beam18.0 m2VerifiedHighSuitable
DEMO-COLUMN-04Concrete Column8.5 m2VerifiedHighSuitable
DEMO-SLAB-03Deck Slab12.0 m4PendingMediumConditional
Decision Readiness
Ready with Restrictions

Evidence requirements are 4/5 satisfied. The unresolved verifier assignment and a separate pending structural recalculation constrain use without blocking procurement preparation.

4/5 evidence requirements satisfied0/1 required specialist assessments complete1 open restrictions

Uncertainty: Structural recalculation is not yet complete

Evidence Fitness

Reliability And Assurance

Partial

Inspection and material records are available; external verifier assignment remains open

Relevance And Contextual Fit

Fit

Evidence is current and relevant to the N203 tender preparation scope

Sufficiency And Gaps

Partial

4 of 5 evidence requirements are satisfied; verifier assignment is unresolved

Specialist Assessments
Structural recalculationPending

Required before unrestricted structural reuse recommendation Owner: Structural engineer.

Restrictions and Outstanding Actions
External verifier assignmentOpen

Independent verification responsibility is not yet assigned

Assign external verifierOpen

Owner: Case owner

Complete structural recalculationIn Progress

Owner: Structural engineer

Procurement Decision Support

Verified engineering data and condition assessments support procurement teams in evaluating reuse opportunities and preparing tender documentation.

Components in this case have been selected based on technical fit, verification status, and circularity potential. Digital Product Passports provide traceability and verification references that can support tender requirements.

Evidence Completeness Checklist
Inspection Report
Structural Capacity Assessment
Material Verification
DPP Link
Verifier Identified
Completion Status4/5 items

Complete and verified data reduces uncertainty and supports decision-making.

Project Decision Overview
Components Selected4
Verified Components3/4
DPP Coverage100%
Structural Evidence Complete75%
Reuse PotentialHigh
Outstanding Actions2

Open actions remain before this case can support an unrestricted decision.